Prices updated: October 2026

Commercial solar cost in Malaysia depends on system size, roof condition, electrical integration and project scope. For businesses considering 100 kWp to 1 MWp systems in 2026, the indicative cost per kWp ranges from RM2,100 to RM1,700 in the examples below. This commercial solar guide compares installed prices, electricity savings, payback and ROI, while explaining Solar ATAP, GITA and financing options. Actual results depend on the applicable TNB tariff, daytime load, export credits, system performance and site assessment.

1.Commercial Solar Cost in Malaysia:
2026 Price Table

The following table compares indicative installed costs for commercial solar systems of different sizes in Malaysia. Larger projects generally have a lower cost per kWp because fixed design and construction expenses are spread across more panels. Prices vary with roof condition, system specifications, electrical works and project scope.

Swipe sideways to see the full table →

System sizeSuitsRoof area needed (sqm)Installed cost (RM)Cost per kWp (RM)Annual generation (kWh)Annual TNB saving (RM)Simple payback (years)
50 kWpShop-lot / small business350117,5002,35065,00033,4753.51
100 kWpSME / small factory700210,0002,100130,00066,9503.14
300 kWpSME / mid-sized factory2,000570,0001,900390,000200,8502.84
500 kWpMid-sized factory3,300900,0001,800650,000196,9504.57
1 MWpLarge factory / industrial plant6,5001,700,0001,7001,300,000393,9004.32
2 MWpLarge industrial facility*13,0003,340,0001,6702,600,000787,8004.24

*The 2 MWp example is outside Solar ATAP’s maximum non-domestic capacity of 1 MW. Other applicable regulatory arrangements would govern an installation of this size.

Note: The figures above are indicative illustrations, not fixed quotations. Final project prices are subject to site survey findings and specific project requirements. Annual generation assumes approximately 1,300 kWh per kWp, while estimated annual savings reflect different illustrative electricity costs and consumption profiles. Annual savings assume that most solar energy generated is consumed on-site and exclude financing costs, operations and maintenance expenses, and tax effects.

2.Why Price per kWp Falls as the System Gets Bigger

System sizeInstalled cost per kWp
100 kWpRM2,100/kWp
500 kWpRM1,800/kWp
1 MWpRM1,700/kWp

The cost per kWp of a commercial solar system generally decreases as the system size increases. This is because certain fixed costs, such as system design, engineering, regulatory applications, project management, testing and commissioning, can be spread across a larger installed capacity.

Aerial view of long rows of solar panels covering the roof of a large factory in an industrial park

Larger projects may also benefit from economies of scale through bulk procurement of solar panels, inverters and other equipment, resulting in a lower overall installation cost per kWp.

For example, the indicative cost decreases from RM2,100/kWp for a 100 kWp system to RM1,700/kWp for a 1 MWp system.

However, a lower cost per kWp does not necessarily mean a lower total project cost. Additional requirements, such as switchboard upgrades, structural reinforcement, longer cable routes or technical assessments, may increase installation costs.

Final pricing remains subject to site survey findings and specific project requirements.

3.What Is Included in a Commercial Solar Quote

A commercial solar quote typically includes solar panels, inverters, mounting structures, electrical integration, engineering, installation, testing, commissioning and monitoring. The following table summarises the main components; the proportion of total cost attributable to each component varies between projects.

ComponentTypical scopeIllustrative cost allocation (RM1 million project)
Solar PV modulesSolar panels and associated module equipment40% / RM 400,000
InvertersString or central inverter configuration10% / RM 100,000
Mounting and structureMetal deck, concrete roof or carport structures10% / RM 100,000
Electrical and MSB IntegrationCabling, protection equipment and Main Switchboard integration18% / RM 180,000
SEDA / TNB / ST requirementsApplications, technical assessments and compliance requirements3% / RM 30,000
Design, EPCC and CommissioningEngineering, procurement, construction, testing and commissioning19% / RM 190,000
Monitoring systemSystem monitoring and performance visibilityIncluded within equipment and integration costs

Note: The cost allocation above is illustrative. Actual component costs and their proportions vary according to equipment specifications, site conditions and the scope of electrical and installation works.

For Solar ATAP projects, certain technical assessment costs may also apply depending on the system size and connection voltage. For non-domestic installations, the current published requirements are:

  • RM1,000 for more than 72 kW up to 180 kW;
  • RM5,000 for more than 180 kW up to 425 kW;
  • RM8,000 for more than 425 kW up to 1 MW; and
  • RM15,000 for a Power System Study (PSS) for a High Voltage connection.

SEDA also publishes a Solar ATAP application fee of RM7.50 per kW of installed capacity. Technical study fees and application fees are separate from the installed system price.

4.Five (5) Factors That Move the Price Up or Down

Aerial view of a factory roof with solar panels arranged around rooftop equipment and skylights

a) Roof Type and Structural Condition

Roof type, condition and layout can significantly influence commercial solar panel installation costs in Malaysia. Metal-deck roofs, reinforced concrete roofs and carports require different mounting systems and installation methods. Older factory roofs may require additional structural assessments before installation. Roof orientation, shading, skylights, existing equipment and maintenance access can also reduce usable installation space, affecting system capacity and overall project costs.

b) Maximum Demand and Tariff Category

For industrial solar and solar for factory projects, system sizing should consider the facility’s applicable TNB tariff, Maximum Demand (MD) and electricity consumption profile. Under the RP4 tariff framework, non-domestic consumers are classified by Low Voltage (LV), Medium Voltage (MV) or High Voltage (HV) supply categories. While solar reduces electricity purchased from the grid, it does not necessarily reduce billed MD charges, particularly where peak demand occurs outside solar generation hours. Accurate system sizing is therefore essential to maximise potential savings.

c) Distance from the Roof to the MSB

The distance between the solar array and the Main Switchboard (MSB) affects installation costs. Longer cable routes require additional cabling, containment, protection equipment and electrical engineering works. Projects involving multiple buildings, difficult cable routing or extensive electrical integration may incur higher costs per kWp compared with installations located closer to the MSB.

d) Structural Reinforcement

Solar panels, mounting structures and associated equipment impose additional loads on existing roofs. Where structural assessments identify inadequate load-bearing capacity, reinforcement of roof members or supporting structures may be necessary. Such works increase installation costs, particularly for older industrial buildings. The extent of reinforcement depends on the building’s structural condition and proposed solar system design.

e) Solar ATAP Capacity Cap

Under Solar ATAP, eligible non-domestic solar PV installations are subject to an inverter output capacity limit of 100% of the consumer’s Maximum Demand or 1,000 kW, whichever is lower, subject to technical assessment. Consequently, available roof space does not necessarily determine the permitted system size. Businesses should also consider daytime electricity consumption and self-consumption potential, as surplus electricity exported to the grid is credited differently from electricity consumed on-site.

5.How Much Can a Business Save?
3 Worked Examples

Commercial solar savings in Malaysia depend on several factors, including the facility’s electricity consumption profile, applicable TNB tariff, solar generation and the amount of solar electricity consumed directly on-site. Businesses with high daytime electricity usage generally have greater potential to maximise self-consumption and reduce electricity purchased from the grid. The actual savings will vary from one facility to another and should therefore be assessed using the customer’s current electricity usage and applicable TNB tariff.

Swipe sideways to see the full table →

MetricSME – 100 kWpMid-sized factory – 500 kWpLarge plant – 1 MWp
Current tariffNon-Domestic LV –
General / ToU, as applicable
Non-Domestic MV –
General / ToU, as applicable
Non-Domestic MV/HV – General / ToU, as applicable
Monthly TNB bill before solar (RM)10,00050,000180,000
Monthly TNB bill after solar (RM)4,42033,587147,175
Indicative saving (%)56%33%18%
Maximum Demand reduction (kW)Not modelledNot modelledNot modelled
Simple payback (years)3.144.574.32
Indicative 25-year cumulative gross savings* (RM)1,673,7504,923,7509,847,500
Indicative gross IRR (%)31.921.723

*The indicative 25-year cumulative gross savings and illustrative gross IRR are based on constant annual electricity savings over 25 years, without discounting the gross savings totals or accounting for system degradation, operations and maintenance, equipment replacement, financing costs, tax effects or future electricity tariff changes. These are simplified financial illustrations and do not represent net lifetime profits or actual project investment returns.

For a 100 kWp solar system, savings are primarily derived from reducing electricity purchased from the grid during daytime operating hours.

For larger systems such as 500 kWp or 1 MWp, savings may also be influenced by the facility’s Maximum Demand, operating schedule, applicable TNB tariff and Solar ATAP requirements.

6.Commercial Solar Payback and ROI in 2026

Commercial solar payback refers to the time required for electricity savings generated by a solar system to recover its initial investment. For example, if a commercial solar system costs RM900,000 and generates approximately RM225,000 in annual gross savings, the simple payback period would be four years, before accounting for operating costs and other financial adjustments.

Depending on project economics, some commercial solar installations in Malaysia may achieve a 3–5-year simple payback. However, actual results depend on installation costs, solar generation, daytime electricity consumption and applicable TNB tariffs.

Businesses can also evaluate long-term financial performance using Return on Investment (ROI), Internal Rate of Return (IRR) and Net Present Value (NPV). Unlike simple payback, IRR and NPV consider projected cash flows over the investment period, providing a more comprehensive assessment of financial returns.

Factors that may improve commercial solar payback include:

  • Lower installed cost per kWp;
  • High daytime electricity consumption;
  • Greater on-site consumption of solar energy;
  • Higher grid electricity costs displaced by solar generation;
  • Eligibility for Green Investment Tax Allowance (GITA), subject to applicable tax requirements; and
  • Effective use of TNB Time-of-Use (ToU) tariffs where suitable for the business’s operating profile.

Conversely, structural reinforcement, electrical upgrades, maintenance expenses, financing costs or lower daytime consumption may affect overall project returns. Businesses should therefore evaluate both simple payback and long-term ROI when considering commercial solar investments.

Learn more in Avera Energy’s TNB Time-of-Use Tariff Guide

7.How GITA Cuts Your Net Cost

The Green Investment Tax Allowance (GITA) can improve the financial returns of eligible commercial solar investments in Malaysia by providing a tax allowance on qualifying capital expenditure. Unlike a cash rebate, GITA reduces taxable income through an allowance against statutory income.

Under MGTC’s 2024–2026 GITA Asset framework, qualifying solar renewable energy systems for a business’s own consumption fall under the 60% GITA category, with the allowance available for set-off against up to 70% of statutory income, subject to applicable conditions.

RM770,400effective after-tax cost
Illustrative GITA Calculation

RM900,000 system cost → RM540,000 GITA allowance (60%) → RM129,600 potential tax savings (24%) → RM770,400 effective after-tax cost.

This illustration assumes that all expenditure qualifies, the company is taxed at 24% and the allowance is fully utilised. Actual tax savings depend on the company’s eligibility, taxable position and applicable tax rate.

Eligibility requirements include:

  • Qualifying solar equipment and eligible capital expenditure;
  • Compliance with MGTC’s application and verification requirements; and
  • Sufficient statutory income to utilise the allowance, subject to applicable set-off limits.

GITA Asset for own consumption is administered by MGTC, while separate GITA Project and GITE Solar Leasing incentives are administered by MIDA.

The Government has also announced enhancements to green technology tax incentives under Budget 2027, including an Investment Tax Allowance of up to 100% for qualifying green technology assets purchased for own consumption. The applicable allowance depends on the relevant incentive category, eligibility requirements and effective tax rules.

Learn more about Malaysia’s GITA tax incentives

8.Zero-Capex Options: PPA, Leasing and Solar Loan

Businesses in Malaysia can adopt commercial solar through financing arrangements such as a Power Purchase Agreement (PPA), solar leasing or solar loan. These options differ in upfront investment, system ownership, payment obligations and long-term savings. While some arrangements require little or no initial capital, they involve ongoing contractual or financing commitments.

Swipe sideways to see the full table →

FeaturePPALeasingSolar Loan
Upfront costUsually zero or minimal, subject to the commercial structureUsually zero or minimal, subject to lease termsDepends on financing package
Who owns the system?Usually solar investor/provider during PPA termUsually lessor during lease, ownership may transfer upon expiryGenerally the business, subject to financing terms
Who gets the savings?Customer benefits from agreed solar energy pricingCustomer benefits subject to lease termsBusiness benefits from solar savings while repaying the loan
TenureProject-specificProject-specificFinancier-specific
Best suited forBusinesses prioritising zero-CAPEXBusinesses preferring fixed lease paymentsBusinesses seeking asset ownership

Under a PPA, the investor typically finances, owns and maintains the solar system, while the business purchases the electricity generated at an agreed tariff.

Solar leasing generally involves periodic payments for the use of the system, while a solar loan enables businesses to finance their purchase and retain ownership, subject to financing terms. Businesses should compare electricity pricing, payment obligations, maintenance responsibilities, early termination provisions and end-of-term ownership.

For projects under Solar ATAP, PPA and leasing arrangements must comply with the applicable programme requirements.

Explore Avera Energy’s commercial solar financing options

9.Solar ATAP for Commercial Users

The Solar Accelerated Transition Action Programme (Solar ATAP) commenced on 1 January 2026, allowing eligible TNB consumers in Peninsular Malaysia to generate rooftop solar electricity for self-consumption and receive credits for surplus energy exported to the grid.

For non-domestic consumers, solar PV inverter output capacity is limited to 100% of Maximum Demand or 1,000 kW, whichever is lower, subject to technical assessment. Systems above 72 kW require a Connection Assessment Study (CAS), while High Voltage connections require a Power System Study (PSS).

Surplus electricity exported by non-domestic consumers is credited at the applicable Average System Marginal Price (Average SMP), subject to the Maximum Allowable Quantity (MAQ) and billing restrictions. Unused export credits cannot be carried forward or used to offset the Automatic Fuel Adjustment (AFA).

Commercial solar systems should therefore be sized primarily around daytime electricity consumption and self-consumption potential to maximise savings.

Solar ATAP operates for 10 years, after which the installation may continue for self-consumption without export credits.

Learn more about NEM vs Solar ATAP in Malaysia

10.Installation Process and Timeline

A commercial solar panel installation in Malaysia typically involves six key stages. The following timelines are indicative and depend on project size, site conditions and regulatory requirements.

Two Avera Energy engineers in hard hats and safety vests inspecting a factory metal roof

1.Site Audit – 1 to 2 weeks

Assess roof condition, structural suitability, installation area, electrical infrastructure, TNB bills, Maximum Demand and electricity consumption patterns.

2.Proposal and System Design – 1 to 2 weeks

Determine the proposed system capacity, equipment specifications, installation cost, estimated electricity generation, savings, payback and ROI.

3.Technical Assessment and Solar ATAP Application – approximately 4 to 8 weeks

TNB or its appointed consultant conducts the applicable Connection Assessment Study (CAS) or Power System Study (PSS). The registered PV service provider then submits the Solar ATAP application through SEDA’s eATAP platform for assessment and approval.

4.Installation – approximately 2 to 8 weeks

Install solar panels, inverters, mounting structures, cabling, protection equipment and monitoring systems following the necessary approvals.

5.Testing and Commissioning – approximately 1 to 2 weeks

Test and commission the completed solar PV system to verify electrical safety, functionality and compliance with technical requirements.

6.Handover – approximately 1 to 4 weeks

Complete the applicable TNB metering and Solar ATAP contractual arrangements, required documentation and final project handover.

Actual project timelines may vary depending on technical studies, regulatory processing, equipment availability and site readiness.

11.Frequently Asked Questions (FAQs)

Commercial solar cost in Malaysia depends on system capacity, equipment specifications, roof condition, structural requirements and electrical integration. Indicative 2026 prices range from RM117,500 for a 50 kWp system to RM1.7 million for a 1 MWp system. Larger installations generally achieve lower costs per kWp, with final pricing subject to site survey findings and project requirements.

The indicative cost per kWp for commercial solar in Malaysia ranges from RM2,350 for a 50 kWp system to RM1,700 for a 1 MWp installation. Larger systems generally benefit from economies of scale, although final pricing depends on equipment specifications, roof conditions, electrical works and any additional technical or structural requirements identified during the site survey.

A 100 kWp commercial solar system in Malaysia has an indicative installed cost of RM210,000, equivalent to RM2,100 per kWp, based on the 2026 pricing examples. The final cost depends on roof suitability, solar panel specifications, mounting structures, electrical integration and any additional installation requirements identified during the site survey.

A 1 MWp commercial solar system in Malaysia has an indicative installed cost of RM1.7 million, equivalent to RM1,700 per kWp. Final pricing depends on site conditions and technical requirements. Under Solar ATAP, non-domestic installations are subject to an inverter output capacity limit of 100% of Maximum Demand or 1,000 kW, whichever is lower.

Commercial solar installations in Malaysia may achieve an indicative simple payback period of approximately 3–5 years, depending on system cost, electricity consumption, daytime self-consumption and applicable TNB tariffs. Businesses with consistently high daytime electricity usage generally have greater potential to maximise solar savings. Actual payback varies by project and is not guaranteed.

A 500 kWp rooftop solar system typically requires approximately 3,300 square metres of suitable roof space, based on the indicative sizing example. The actual area depends on solar panel dimensions, roof orientation, shading, structural suitability, equipment placement, required setbacks and maintenance access. A site survey is necessary to determine the available installation capacity.

Yes. Businesses in Malaysia may adopt commercial solar with little or no upfront capital through a Power Purchase Agreement (PPA) or eligible solar leasing arrangements. Solar loans may also reduce initial capital requirements, depending on financing terms. These options involve ongoing payment obligations, with system ownership, savings and contractual responsibilities varying by arrangement.

Yes. Qualifying commercial solar investments in Malaysia may benefit from the Green Investment Tax Allowance (GITA). Under MGTC’s published 2024–2026 GITA Asset framework, eligible solar renewable energy systems for own consumption generally qualify for a 60% allowance on qualifying capital expenditure, subject to the applicable eligibility requirements, statutory income set-off limits and tax conditions.

12.Request a Commercial Solar Proposal

Every commercial or industrial facility in Malaysia has unique energy requirements and site conditions.

Request a commercial solar proposal tailored to your site, covering installation cost, projected electricity savings and estimated payback. Avera Energy aims to deliver an initial proposal within five (5) working days upon receiving the necessary site information and electricity bills.

Contact Avera Energy for a site-specific commercial solar assessment.

Other Articles

Two Avera Energy engineers in safety vests and helmets inspecting a commercial rooftop solar system beside an inverter, one holding a tablet

Solar Panel Maintenance in Malaysia: Cost, Schedule and O&M Guide for Commercial Systems (2026)

Aerial view of a ground-mounted solar farm with a grid substation, surrounded by green hills

Renewable Energy Certificates (REC) in Malaysia: mREC, I‑REC and How to Buy Them (2026)