Last updated: October 2026

Malaysia’s Large Scale Solar (LSS) programme supports utility-scale renewable electricity through competitive procurement. For companies evaluating a solar farm in 2026, understanding LSS5, LSS5+ and the newly announced LSS6 is essential before committing land or capital. Each LSS round has its own capacity allocations, bidding rules and delivery milestones. This guide explains how LSS Malaysia works, summarises publicly reported awards, outlines LSS6 solar-and-battery requirements and identifies the commercial and regulatory considerations for developing or investing in a large scale solar project.

1.What Is the Large Scale Solar (LSS) Programme?

The large scale solar Malaysia framework, also known as the Large Scale Solar (LSS) programme, is a competitive procurement framework under which the Energy Commission selects eligible developers to build, finance and operate grid-connected solar PV plants. The current federal LSS procurement rounds addressed here concern Peninsular Malaysia. Separate electricity-sector arrangements apply in Sabah and Sarawak and a project in either state should not be assumed eligible for these bids.

Avera engineer with a tablet checking string inverters and combiner boxes at a ground-mounted solar farm

Unlike rooftop solar for a customer’s own consumption, an LSS solar farm primarily supplies electricity into the power system. In a conventional LSS arrangement, the selected project company enters into a Solar Power Purchase Agreement (SPPA) with the designated electricity purchaser, generally Tenaga Nasional Berhad (TNB) in Peninsular Malaysia, subject to the applicable award and agreement terms. Energy payments depend on metered production and the applicable agreement terms, rather than a guaranteed fixed annual revenue.

The Energy Commission’s published LSS guidelines provide for a 21-year SPPA term under that framework. That historical term is useful for planning but should not be assumed unchanged for LSS6 without reviewing its actual RFP and project documents. LSS development also involves grid studies, land rights, environmental and planning approvals, financing, engineering, construction and commissioning. These obligations make solar farm viability highly site-specific.

2.LSS Rounds So Far: LSS1 to LSS5

Malaysia’s Large Scale Solar (LSS) programme has progressed through several competitive bidding rounds, supporting the development of utility-scale solar generation. Each round has introduced new capacity allocations and project opportunities, contributing to the expansion of large scale solar in Malaysia.

The table below summarises the awarded capacity and reported project status of LSS1 to LSS5, based on published information from the Energy Commission.

Swipe sideways to see the full table →

LSS roundBid cycleAwarded capacityReported project status
LSS12016354 MW14 projects operational as of July 2025
LSS22017–2018466 MW26 projects operational as of July 2025
LSS32019491 MW5 projects operational as of July 2025
LSS4 / LSS@MEnTARI2020–2021823 MW27 projects operational as of July 2025
LSS5 / LSS PETRA20241,904 MW27 projects awarded, as announced in November 2025

The earlier LSS rounds established Malaysia’s utility-scale solar market, while subsequent rounds increased procurement opportunities for developers and investors. LSS5 represented a further expansion, with 27 projects totalling 1,904 MW awarded, according to the Energy Commission’s November 2025 announcement.

Importantly, awarded capacity does not necessarily represent operational capacity. A successful LSS project must complete the applicable development, financing, construction, testing and commissioning requirements before commencing commercial operations.

The operational figures above reflect the Energy Commission’s July 2025 reporting, rather than the operational status of all projects as at October 2026. Developers and investors should therefore distinguish between awarded projects and commissioned solar farms when assessing Malaysia’s LSS market.

3.LSS5 and LSS5+: What Was Awarded

Malaysia’s Large Scale Solar (LSS) programme expanded significantly through LSS5 (LSS PETRA) and LSS5+ (LSS PETRA 5+), creating further opportunities for solar farm development and investment.

According to the Energy Commission’s announcement dated 13 November 2025, LSS5 recorded 27 selected projects totalling 1,904 MW, with an average awarded price of 17.0 sen/kWh. LSS5+ recorded 13 selected projects totalling 1,975 MW, with an average awarded price of 15.2 sen/kWh. Together, both rounds represented 3,879 MW across 40 projects.

3,879 MWacross 40 projects
LSS5 and LSS5+ combined

LSS5: 27 projects, 1,904 MW, 17.0 sen/kWh average.
LSS5+: 13 projects, 1,975 MW, 15.2 sen/kWh average.

The two rounds had different bidding structures:

Swipe sideways to see the full table →

ProgrammePackageProject capacity rangeOffered quota
LSS5Package 11 MW to below 10 MW250 MW
Package 210 MW to below 30 MW250 MW
Package 330 MW to 500 MW1,000 MW
Package 4 (floating solar)10 MW to 500 MW500 MW
LSS5+Package A (ground-mounted)30 MWac to 500 MWac1,500 MWac
Package B (floating solar)10 MWac to 500 MWac500 MWac

LSS5 projects were initially scheduled to commence commercial operations in 2026, while LSS5+ projects were scheduled from 2027. Actual commercial operation dates remain subject to project-specific requirements, approvals and contractual milestones.

These historical average prices should not be treated as guaranteed tariffs or benchmarks for future LSS rounds, particularly projects incorporating battery energy storage systems.

4.LSS6: What to Expect

Rows of battery energy storage system containers beside a power transformer at a utility-scale energy site

Malaysia’s sixth Large Scale Solar (LSS6) programme, announced in July 2026, introduces battery energy storage systems (BESS) alongside utility-scale solar development in Peninsular Malaysia. The Energy Commission announced allocations totalling 2,650 MW of solar capacity and 1,250 MW / 5,000 MWh of BESS.

2,650 MWsolar capacity
LSS6 allocations, announced July 2026

Plus 1,250 MW / 5,000 MWh of battery energy storage (BESS).

Swipe sideways to see the full table →

LSS6 packageSolar allocationBESS allocationParticipation
Hybrid Package 12,200 MW1,100 MWEligible developers
Hybrid Package 2300 MW150 MWEligible Bumiputera developers
Solar Package 3150 MWNot requiredEligible Bumiputera developers

The two hybrid packages combine 2,500 MW of solar capacity with BESS, while Package 3 provides a separate 150 MW solar-only allocation for smaller Bumiputera projects. Individual project capacities range from 60–500 MW for Packages 1 and 2, and 10–30 MW for Package 3.

LSS6 introduces additional requirements and priorities for developers. Solar project development experience is required, although previous BESS experience is not mandatory. The July 2026 programme announcement also identified preferences for locally manufactured renewable-energy equipment and projects in areas with growing electricity demand.

Expected LSS6 Timeline

LSS6 projects are expected to commence commercial operations in phases, with full commercial operation targeted by 31 December 2029, subject to project-specific requirements and approvals.

LSS6 is expected to create further opportunities for large scale solar Malaysia development and investment. Prospective developers and investors should assess site suitability, grid connection, financing and storage requirements before pursuing a project. Project awards, tariffs and individual commissioning schedules remain subject to official confirmation.

Learn more about BESS in Malaysia

5.Who Can Bid: LSS Eligibility Requirements

Eligibility for Malaysia’s Large Scale Solar (LSS) programme depends on the bidding round and package. The Energy Commission invites experienced companies and consortia with the technical and financial capabilities to develop, finance and operate utility-scale solar projects.

For LSS6, the principal eligibility and project-development considerations include:

Screening areaKey requirements and considerations
Corporate and ownershipEligible company or consortium structure, including applicable Bumiputera participation requirements for LSS6 Packages 2 and 3.
Technical experiencePrevious solar project development experience is required. Prior BESS experience is not mandatory under LSS6.
Financial capacityDemonstrated financial capability to develop, finance, construct and operate the proposed project, subject to tender requirements.
Land and approvalsSuitable project land, secure land rights and applicable planning, environmental and development approvals.
Grid connectionFeasible grid connection, network capacity and compliance with applicable technical and interconnection requirements.
RFP complianceCompliance with package-specific eligibility criteria, technical specifications, documentation and submission requirements.

LSS6 also prioritises bidders using domestically manufactured renewable-energy products, including solar PV modules, and projects in areas experiencing strong electricity demand growth.

The Energy Commission’s general LSS guidelines provide for at least 51% Malaysian equity participation, subject to any higher or package-specific threshold set by the Commission. LSS6 applicants must also check the applicable Bumiputera criteria and detailed RFP terms.

Prospective developers and investors should verify the applicable tender conditions and undertake corporate, technical, land and grid assessments before making binding project commitments.

6.LSS Bidding Process and Timeline

Developing a Large Scale Solar (LSS) project in Malaysia involves competitive bidding, technical assessments, regulatory approvals, financing and construction. The following steps outline the typical process under the Energy Commission’s LSS framework.

  1. Review the opportunity and RFP.
    Assess the applicable programme, eligibility criteria, project capacity and tender requirements. Obtain the Request for Proposal (RFP) documents during the designated period.
  2. Conduct feasibility studies.
    Evaluate land suitability, solar yield, grid connectivity, technical design, project costs and financing requirements. Include battery energy storage system (BESS) considerations where applicable.
  3. Prepare and submit the bid.
    Submit the technical and commercial proposals, proposed electricity tariff and supporting documents by the prescribed deadline.
  4. Bid evaluation and award.
    The Energy Commission evaluates submissions and notifies selected bidders. The assessment period depends on the applicable tender schedule.
  5. Complete grid assessments.
    Undertake the required feasibility, grid impact or power system studies and finalise interconnection requirements. Preliminary assessments may begin before award.
  6. Execute the SPPA.
    Finalise and execute the Solar Power Purchase Agreement with the relevant electricity utility, subject to applicable requirements.
  7. Achieve financial close.
    Finalise financing documents and satisfy the relevant funding conditions before progressing with project implementation.
  8. Construct and commission.
    Complete construction, grid interconnection, testing and commissioning before achieving the commercial operation date (COD).

Indicative Timeline

Project preparation and bid evaluation may take several months, while financing, construction and commissioning can extend over several years. These are general planning expectations, not prescribed durations. Actual milestones depend on the applicable RFP, project agreements and regulatory approvals.

For LSS6, commercial operations are expected to commence in phases, with full implementation targeted by 31 December 2029.

7.LSS Economics: Tariffs, Capex and Returns

The financial viability of a Large Scale Solar (LSS) project in Malaysia depends on electricity tariffs, capital expenditure (capex), solar generation, financing costs and operating performance. Solar farms incorporating battery energy storage systems (BESS) also require additional investment and operational considerations.

The following table outlines key financial metrics for evaluating an LSS investment.

Financial metricIndicative benchmark or consideration
Historical LSS tariffs15.2–17.0 sen/kWh, representing the reported average awarded prices for LSS5+ and LSS5 respectively. Not indicative of future tariffs.
Capital cost per MWProject-specific; depends on plant capacity, equipment, BESS, land, grid connection and construction requirements.
Capacity factor20% assumed for illustration only; actual generation requires a site-specific solar yield assessment.
Indicative project IRRProject-specific; determined through financial modelling of revenue, capex, operating costs, taxes and financing assumptions.

For illustration, a 100 MWac solar farm operating at an annual capacity factor of 20% would generate approximately 175,200 MWh annually, assuming the capacity factor reflects net electricity delivered. Actual output will vary with irradiation, system availability, degradation and other operating conditions.

175,200 MWha year, illustrative
100 MWac solar farm at a 20% capacity factor

Assuming the capacity factor reflects net electricity delivered.

Historical LSS tariffs should not be treated as guaranteed returns or pricing benchmarks for LSS6 projects incorporating BESS.

Before investing in large scale solar Malaysia projects, developers and investors should undertake independent technical assessments and financial modelling to evaluate project feasibility, expected returns and investment risks.

8.How to Invest in or Partner on a Solar Farm in Malaysia

Investing in large scale solar Malaysia projects can involve direct development, joint ventures, land partnerships or equity investment. The appropriate structure depends on project feasibility, funding requirements and applicable Large Scale Solar (LSS) regulations.

Aerial view of a large ground-mounted solar farm with rows of solar panels, a substation and access roads among green hills

1. Direct LSS Project Development

Eligible companies or consortia may participate directly in LSS bidding rounds. Avera Energy can support project feasibility, site assessment, engineering, regulatory approvals, construction and commissioning, subject to agreed project scope.

2. Joint Venture with a Solar Developer

Investors or project owners may collaborate with an experienced developer to combine land, capital and technical expertise. Avera can explore joint development opportunities, including project structuring, technical coordination and delivery, subject to mutually agreed terms and regulatory requirements.

3. Landowner Partnerships

Landowners with suitable sites may explore leasing their land for solar farm development. Avera can assess site suitability, grid connectivity and development potential. Lease arrangements remain subject to land rights, regulatory approvals and commercial agreement.

4. Equity Investment in Solar Projects

Investors may explore acquiring equity interests in eligible LSS project companies, subject to applicable ownership restrictions and approvals. Avera can discuss potential investment partnerships and provide development and project-management expertise where agreed.

Partner with Avera Energy

From feasibility and investment structuring to construction and long-term asset management, Avera Energy provides integrated large scale solar development services.

Explore our Large Scale Solar services to discuss potential collaboration opportunities.

All arrangements remain subject to project feasibility, applicable approvals and mutually agreed commercial terms.

9.FAQ

Large Scale Solar (LSS) is a competitive bidding programme administered by the Energy Commission to develop utility-scale solar power plants. Selected project companies sell electricity generated by their solar farms under a Solar Power Purchase Agreement (SPPA) with the designated electricity purchaser.

LSS5, officially known as LSS PETRA, is Malaysia’s fifth large scale solar bidding round. In November 2025, the Energy Commission reported 27 selected projects totalling 1,904 MW, with an average awarded tariff of 17.0 sen/kWh. LSS5+ is a separate, additional bidding round.

LSS6 was announced in July 2026. The programme targets phased commercial operations, with full implementation expected by 31 December 2029. Actual project timelines depend on regulatory approvals and project requirements.

Eligible companies and consortia meeting the Energy Commission’s technical, financial and ownership requirements may participate. Eligibility varies by bidding round and package, including specific Bumiputera participation requirements under LSS6.

There is no fixed tariff applicable to all LSS projects. The average awarded tariffs for LSS5 and LSS5+ were 17.0 sen/kWh and 15.2 sen/kWh, respectively. Actual tariffs depend on the relevant bidding results and contractual arrangements.

A utility-scale solar farm may require approximately 5–10 acres per MW, based on an indicative estimate published by the Energy Commission. Actual land requirements depend on system design, site conditions, equipment layout and whether capacity is measured in MWac or MWp.

The Energy Commission’s published LSS guidelines specify a 21-year SPPA term. Developers should confirm the applicable tenure and conditions under the relevant bidding round and project agreements.

Foreign companies may participate through eligible investment or consortium structures, subject to the applicable bidding requirements. For example, LSS5+ required at least 51% Malaysian equity participation. Foreign ownership requirements for LSS6 must be verified against its specific tender conditions.

10.Partner with Avera on Your Next Solar Project

Partner with Avera on your next large-scale solar project. Whether you have a potential site, a development opportunity or an investment proposal, contact Avera Energy to discuss preliminary land, grid, technical and commercial feasibility. Every solar farm opportunity remains subject to due diligence, approvals and agreed commercial terms.

Partner with Avera on your next large-scale solar project.

Other Articles

Two Avera Energy engineers in safety vests and helmets inspecting a commercial rooftop solar system beside an inverter, one holding a tablet

Solar Panel Maintenance in Malaysia: Cost, Schedule and O&M Guide for Commercial Systems (2026)

Aerial view of a ground-mounted solar farm with a grid substation, surrounded by green hills

Renewable Energy Certificates (REC) in Malaysia: mREC, I‑REC and How to Buy Them (2026)